Project Management Scheduling

Existing project management systems include functionality to produce schedules (called ‘leveling’ or ‘scheduling’).  OTS has devloped algorithms that use ‘squeaky wheel’ optimization to outperform this existing functionality.  The following table shows typical results obtained by comparing OTS algorrithms with the Primavera leveler for actual projects from the construction industry.

 
Approx # of Activities
Improvement Over Primavera leveler
Project Duration
Resource Overload
Municipal Utility
2700
14%
32%
Residential Home Construction
12300
30%
0%*
Manufacturing Facility
33000
13%
0%*
Oil Refinery Facility Maintenance
12200
15%
74%

*the initial schedule had no overload

The following snapshot shows schedule optimization in PSOP for an aircraft assembly problem. The Primavera-leveled schedule is on top and the PSOP schedule on the bottom. Overload is shown in red. The PSOP schedule eliminates all (100%) of the overload and is approximately 30% shorter as well.